Use flow meter totalizer readings to verify daily solar pump delivery and document test conditions, shortfalls and acceptance criteria.

Set the measurement boundary
Agree whether the client is accepting volume delivered to the storage tank or volume supplied to the irrigation zones. Put the measurement point on the drawing and identify any bypass or branch that would divert water before the delivery point. Select a meter with a documented range that covers low morning flow as well as the expected afternoon flow, and follow its installation and calibration instructions.
Record total volume over an agreed test window
Take opening and closing photos of the same totalizer in the same units. Note the dates, test hours, zone configuration, changes in water level, and periods on PV or AC backup. In a hypothetical test the register rises from 126.4 to 151.1 m³, so delivery was 24.7 m³ in the observation window. If the agreed target for those conditions was 25.0 m³, record a 0.3 m³ shortfall and review the contract tolerance before sign-off.
Decide what needs a retest
A momentary flow rate, inverter frequency or app estimate answers a different question from the accumulated volume. If the meter resets, loses readings or operates outside its range, document the interruption and schedule a repeat. A mixed-source total should only be reported as PV-only delivery if separately metered or independently logged for the same interval.
What to send with a quotation request
Send the required m³ per day, operating head, meter location and range, test window, allowable tolerance, backup arrangement and responsibility for commissioning. This makes it possible to price the drive and the measurement equipment separately.